File #: 2010-0263    Version: 1
Type: Motion Status: Passed
File created: 4/26/2010 In control: Government Accountability and Oversight Committee
On agenda: Final action: 6/1/2010
Enactment date: Enactment #: 13246
Title: A MOTION approving a report on the options and recommending a strategy for providing emergency backup power for the South treatment plant in Renton as required in a 2009 budget proviso.
Sponsors: Larry Phillips
Indexes: Renton, City of, Wastewater
Attachments: 1. 13246.pdf, 2. A. Report on Options and Recommendation of a Strategy for Providing Emergency Backup Power for the South Treatment Plant, 3. 2010-0263 Fiscal Note.xls, 4. 2010-0263 Transmittal Letter.doc, 5. 2010-0263 staff report Back power Alts for South TP (05-18-10), 6. A. Report on Options and Recommendation of a Strategy for Providing Emergency Backup Power for the South Treatment Plant
Staff: Mountsier, Beth
Drafter
Clerk 04/19/2010
title
A MOTION approving a report on the options and recommending a strategy for providing emergency backup power for the South treatment plant in Renton as required in a 2009 budget proviso.
body
      WHEREAS, King County in response to heightened risk of flooding of the Green river due to seepage at the Howard Hanson dam has taken steps to prepare for a potential flood, and
      WHEREAS, an interruption of electrical power at the South treatment plant was one of many concerns with regard to potential flooding, and
      WHEREAS, as an interim measure, backup power has been provided through a lease of diesel generators that were installed on a temporary basis at the South treatment plant, and
      WHEREAS, it will likely take several years to improve levees and repair the Howard Hanson dam so that flooding becomes much less of a threat, and
      WHEREAS, the King County council has requested that the King County executive provide a report to the council analyzing the options and recommending a strategy for providing emergency backup power for the South treatment plant in Renton in the future, and
      WHEREAS, the risk of flooding has been reduced by actions taken by the United States Army Corps of Engineers to install an interim grout curtain, and
      WHEREAS, the risk of power outages has also been reduced by actions taken by Puget Sound Energy to protect its infrastructure, and
      WHEREAS, these improvements reduce risk of power loss at the South treatment plant to the extent that backup generators are no longer needed;
      NOW, THEREFORE, BE IT MOVED by the Council of King County:
      The report addressing the wastewater treatment division's analysis of the options
and recommending a strategy for providing emergency backup power at South treatment plant in Renton is hereby approved.