Title: A MOTION authorizing the King County executive to enter into an interlocal agreement with Tacoma Public Utilities to implement restoration projects at Auburn Narrows on the Green river.
Sponsors: Julia Patterson
Indexes: Auburn, City of, Green River , Interlocal Agreement, Tacoma, City of
Attachments: 1. 2003-0391 AUBURN_NARROWS PROJECT Presentation.ppt, 2. 2003-0391 Staff Report Auburn Narrows.doc, 3. 2003-0391 Transmittal Letter.doc, 4. A. Interlocal Agreement Between King County and the City of Tacoma, Department of Public Utilities, Water Division to Implement Restoration Projects at Auburn Narrows on the Green River
Staff: Reed, Mike
Drafter
Clerk 08/20/2003
title
A MOTION authorizing the King County executive to enter into an interlocal agreement with Tacoma Public Utilities to implement restoration projects at Auburn Narrows on the Green river.
body
WHEREAS, the city of Tacoma, Department of Public Utilities, Water Division (doing business as and referred to in this ordinance as "Tacoma Water") withdraws water from the Green river in King County as a principal source of potable water supply for the city of Tacoma and its customers, and
WHEREAS, in its 1987 Tacoma Comprehensive System Water Plan, Tacoma Water identified the need for a second supply pipeline from the Green river, and as part of water plan implementation, designed and permitted a pipeline that runs from the diversion works on the Green river through south King County to the existing water supply system near Tacoma ("Pipeline 5"), and
WHEREAS, as construction of Pipeline 5 necessitated crossing a number of streams and wetlands in King County, the county required Tacoma Water to develop a comprehensive mitigation plan that was approved by the King County council in 1993 through Ordinance 10776, and
WHEREAS, the mitigation plan required both on-site mitigation wherever wetlands were impacted by construction, and an additional amount of offsite compensatory wetland mitigation to account for the temporal loss of wetland values that could not be mitigated at the impact sites, and
WHEREAS, the plan also created an environmental resource fund that would over time make available two million five hundred thousand dollars to be used by King County for the purposes of acquiring and restoring fish habitat, protecting wildlife and water resources, and providing recreational opportunities within the Green river basin, and
WHEREAS, in 1995, the King-County-owned Auburn Narrows park property was identified as a candidate site for Tacoma Water's offsite wetland impact mitigation activities, and King County and Tacoma Water ...

Click here for full text