title
AN ORDINANCE making a disappropriation and reappropriation of $15,000,000 to the HMC/MEI 2000 projects fund to provide sufficient flexibility in the construction of the inpatient expansion project at Harborview Medical Center, and a reconfiguration of the 9th and Jefferson project; and amending the 2006 Budget Ordinance, Ordinance 15333, Section 114, as amended, and Attachment B, as amended.
body
BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:
SECTION 1. Ordinance 15333, Section 114, as amended, is hereby amended by adding thereto and inserting therein the following:
From several capital improvement project funds there is hereby appropriated and authorized to be disbursed the following amounts for the specific projects identified in Attachment A to this ordinance.
Fund Capital Fund Name Amount
3791 HMC/MEI 2000 Projects $0
PROVIDED THAT:
No funds of the $15,000,000.00 transferred by this ordinance in Fund 3791 from Project 379006 to Project 379004 may be expended or encumbered until the executive and the University of Washington file with the clerk of the council a certification that:
1. A settlement agreement has been signed by Turner Construction Company, Harborview Hospital, the University of Washington and King County resolving cost claims from the contractor's requests for equitable adjustment on the Inpatient Expansion Building ("IEB");
2. The settlement is in substantially the form set forth in the agreement draft dated March 30, 2006 and sent that date by the Attorney General's Office on behalf of the University of Washington to the prosecuting attorney and the council's legal counsel; and
3. The settlement agreement contains a provision in substantially the following form: "If Owner terminates any portion of the Work for convenience, the Parties shall mutually determine how to adjust the Contract Time. In addition, if a portion of the NJB is terminated for convenience, Owner agrees (subject to approval by the County Council) to merge the remaining NJB work with the IEB thereby creating one project. The Contract will then be amended to reflect a revised single MACC for the IEB and NJB (including a negotiated amount for the MACC contingency), and a revised GCC cost and Fee. As stated above, the Fee will be adjusted to an amount that will cover only the actual cost of B&O tax and bonds."
SECTION 2. Attachment A to this ordinance hereby amends Attachment B to Ordinance 15333, as amended, by adding thereto and inserting therein the projects listed in Attachment A to this ordinance.