Title: AN ORDINANCE relating to fees and other charges assessed by the real estate services section for processing applications and authorizing use of King County property through right-of-way construction permits; and amending Ordinance 1711, Section 4, as amended, and K.C.C. 14.44.040.
Sponsors: Julia Patterson
Indexes: Fees, Permits, Right-of-Way
Code sections: 14.44.040 -
Attachments: 1. 2011-0485 fiscal note.xls, 2. 2011-0485 transmittal letter.doc, 3. 03-06-12 Staff Report with attachments.pdf, 4. 05-15-12 Staff Report with attachments, 5. 2011-0485 Hearing Notice re right-of-way construction permits DRAFT.doc
Drafter
Clerk 11/17/2011
Title
AN ORDINANCE relating to fees and other charges assessed by the real estate services section for processing applications and authorizing use of King County property through  right-of-way construction permits; and amending Ordinance 1711, Section 4, as amended, and K.C.C. 14.44.040.
Body
      BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:
      SECTION 1.  A.  Section 2 of this ordinance proposes changes to the fee structure currently charged for right-of-way construction permits by consolidating fees into fewer categories and proposing a maximum fee for right-of-way construction permits.
      B.  These fees are established and assessed pursuant to K.C.C. 2.99.030.
      SECTION 2.  Ordinance 1711, Section 4, as amended, and K.C.C. 14.44.040 is hereby amended as follows:
      Each application requires a fee payable to the real estate services section for the administrative costs and expenses of processing the application.  The following fee schedule applies:
      ((A.  Pole lines:
            Power, telephone, etc. (every six poles or portion thereof):       $200.00
      B.  Water:
            Installing mains (1000 lin. ft. or less):                  $200.00
            Additional 1000 lin. ft. or fraction thereof:                  $180.00
            Excavation for connection:                              $200.00
      C.  Sewer:
            Installation of mains (1000 ft. or fraction thereof):            $200.00
            Additional 1000 lin. ft. or fraction thereof:                  $180.00
            Excavation for connection:                              $200.00
      D.  Cable or conduit:
            Installing cable or conduit (1000 ft. or less):                  $200.00
            Additional 1000 lin. ft. or fraction thereof:                  $180.00
            Excavation for connection:                              $200.00
      E.  Gas or oil:
            Installing mains (1000 lin. ft. or less):                  $200.00
            Additional 1000 ft. or fraction thereof:                  $180.00
            Excavation for connection:                              $200.00
      F.  Attachment to existing poles for every three attachments:      $140.00))
      A.  Level One (Basic or Minimum Fee):      $200.00
      A Level One fee shall be charged for a single residential connection; a single excavation; one thousand linear feet or less of main pipe, cable or conduit; or one to six poles or attachments.
      B.  Level Two:      $500.00
      A Level Two fee shall be charged for two to three separate excavations; one thousand one to three thousand linear feet of main pipe, cable or conduit; or seven to fifteen poles or attachments.
      C.  Level Three:      $1,000
      A Level Three fee shall be charged for four to seven separate excavations; three thousand one to seven thousand linear feet of main pipe, cable or conduit; or sixteen to thirty poles or attachments.
      D.  Level Four (maximum fee):      $2,000
      A Level Four fee shall be charged for eight or more separate excavations; seven thousand one or more linear feet of main pipe, cable, or conduit; or more than thirty-one poles or attachments.
      ((G.)) E.  Immediate response permit requests:  In addition to the required permit fees, an additional fee of ((sixty)) one hundred twenty dollars shall be charged.
      ((H))F.  Annual ((M))maintenance permits:  Fees per number of connections:
        1.  0 to 50 connections:                                    $200.00
        2.  51 to 100 connections:                                    $250.00
        3.  101 to 200 connections:                                    $300.00
        4.  201 to 500 connections:                                    $400.00
        5.  501 or more:                                          $450.00